Utility Works Cause Traffic Diversion on Jalan Jenderal Gatot Subroto

The Jakarta Transportation Agency (Dishub) is detouring a traffic flow on Jalan Jenderal Gatot Subroto, South Jakarta, in connection with Telkom utility network work.

The work site is on the north side of Jalan Jenderal Gatot Subroto

Jakarta Transportation Agency (Dishub) Head, Syafrin Liputo said, utility network work will be ongoing from November 24 to December 8, 2025.

"The work site is on the north side of Jalan Jenderal Gatot Subroto, from the Denpasar Transjakarta Bus Stop to just before Jalan Denpasar," he expressed, Friday (11/28).

Construction Quality and Supervision Must Be Tightened for Mutiara Dam Repairs

He explained, reduction or narrowing of the road body will occur during the construction work. Additionally, the Transjakarta separator, approximately 350 meters long, will be torn down, to optimize lane consistency.

"Thus, the Transjakarta bus becomes mixed traffic and is reinstalled after the work is completed," he explained.

To support the work, traffic engineering is carried out according to the work stages, as follows:

a. Pit 1 Work

1. The excavation point is on the left side of the regular lane next to the Transjakarta Denpasar Bus Stop

2. Work will commence on November 24, 2025, at 10 AM until December 1, 2025, at 4 AM

3. During the work, there will be a reduction in the width of the road

b. Pit 2 Work

1. The excavation point is on the left side of the regular lane in front of the Patra Jasa building (HDD machine)

2. The work will start on November 26, 2025, and end on December 5, 2025

During the work, there will be a reduction in the road width

c. Pit 3 Work

1. The excavation point is on the left side of the regular lane in front of CFX Tower (HDD machine)

2. The work will start from December 6, 2025, to December 14, 2025

3. During the work, there will be a reduction in the road width

d. Pit 4 Work

1. The excavation point is on the left side of the regular lane next to the Kuningan Flyover before Jalan Denpasar (Balai Kartini building)

2. The work will start on December 5, 2025, at 10 PM until December 8, 2025, at 4 AM

3. During the work, there will be a reduction in road width

"Work at pit 1 and pit 4 is only done on holidays or weekends," he stated.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1783 personFakhrizal Fakhri
  2. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1556 personFakhrizal Fakhri
  3. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1151 personFakhrizal Fakhri
  4. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1132 personFakhrizal Fakhri
  5. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye1127 personBudhi Firmansyah Surapati